The Change Working Time dialog is used to change the working time in project calendar. This dialog appears on clicking the Change Working Time button on the toolbar.

The Change Working Time dialog provides options as follows:

Option Purpose
For calendar Specify the calendar you wish to select.
Add New Calendar Create a new calendar or a copy of a calendar based on default or custom calendar.
Manage Custom Calendars Add or remove custom calendar.

The following image shows the Change Working Time dialog:

The Change Working Time dialog displays three tabs, namely Calendars, Work Weeks, Exceptions. The Calendars tab displays a calendar where you can click a day to view the working time based on the work week, and check whether or not to honor default calendar exceptions.

Work Weeks

The Work Weeks tab provides option to change the default work week for project calendar, resource calendar, or for any custom calendar that you create. You can also choose or create additional schedule for a range of days that differ from the default work day.

The following image shows the Work Weeks tab:

The Work Week tab provides various options as follows:

Option Purpose
Select day(s) Select one or more days that constitute a work week.
Name Specify a name for a working week.
Start Date Specify the Start date for a working week.
Finish Date Specify the Finish date for a working week.

Once you select the day(s) you want to change from a working day to non-working day or vice versa, you can choose one of the following:

Exceptions

The Exceptions tab provides you the option to add exceptions in the calendar such as marking public holidays or vacation. The following image shows how this tab appears at runtime:

The Exception tab provides options as follows:

Option Purpose
Start date Shows a drop-down menu with a calendar to select the start date of exception.
End by Shows a drop-down menu with a calendar to select the end date of exception.
Recurrence Pattern Shows a button to set a repeat on an exception throughout the schedule. Clicking this button opens Recurrence Pattern dialog that lets you specify the days on which recurrence appear. Any task scheduled around an exception automatically gets rescheduled.

The following image shows how the Recurrence Pattern dialog appears at runtime: